Skip to content
hoodpedia
  • Home
  • People
  • Organizations
Add entrySubmit
hoodpedia
  • Home
  • People
  • Organizations
  • Search
  • Add entry
  • About
hoodpedia

The open encyclopedia of founders, entrepreneurs and startups. Written by the community, corrected by the people it describes.

Browse

  • People
  • Organizations
  • Recently added
  • Verified entries

About

  • How hoodpedia works
  • Claim your entry
  • Editing guidelines
  • Data sources

Entries are compiled from published sources and reviewed before they go live.

hoodpedia - Bengaluru

HomeOrganizationsPower Grid Corporation of India

Organization · Company

Power Grid Corporation of India

Power Grid Corporation of India Limited is an Indian central public sector undertaking under the Ministry of Power that owns and runs the country's inter state electricity transmission system. It was incorporated in October 1989 as the National Power Transmission Corporation and renamed Power Grid in October 1992. It moves about half of the electricity generated in India, and it is one of the few companies on the Indian grid whose main product is the wire between the power station and the city.

Suggest edit
Last edited 16 October 20263 revisions17 sourcesReading time 31 min
Power Grid Corporation of India

Power Grid Corporation of India

Entrant since 2026 · Organization · Company · Awaiting verification

Summary details for Power Grid Corporation of India
Full namePower Grid Corporation of India Limited
National Power Transmission Corporation Limited until 23 October 1992
Founded23 October 1989
incorporated under the Companies Act 1956
FounderGovernment of India
under the Ministry of Power
HeadquartersGurugram, Haryana
Chairman and managing directorVamsi Rama Mohan Burra
SectorBulk power transmission, telecom and transmission consultancy
Transmission networkAbout 1,68,140 circuit kilometres and 252 substations
Transformation capacityAbout 4,22,430 MVA as of 31 January 2021
Share of the countryTransmits about 50 per cent of the power generated in India
RevenueAbout 46,913 crore rupees in the year 2023-24
Net profitAbout 15,573 crore rupees in the year 2023-24
ShareholdingGovernment of India holds about 51.34 per cent
Employees8,316 in March 2024
StatusMaharatna central public sector undertaking
Navratna in May 2008 and Maharatna in October 2019
ListedBSE and NSE
BSE 532898, NSE POWERGRID
DivisionsPowertel India Limited and Central Transmission Utility of India Limited
Websitepowergrid.in

Timeline

  1. 1989Power Grid is incorporated on 23 October as the National Power Transmission Corporation Limited with an authorised share capital of 5,000 crore rupees.Authorised capital was raised to 10,000 crore rupees in 2007-08.
  2. 1990The company receives its Certificate for Commencement of Business on 8 November.
  3. 1991Management begins functioning in August and starts taking over transmission assets from NTPC, NHPC, NEEPCO and Neyveli Lignite in phases.
  4. 1992The name is changed to Power Grid Corporation of India Limited on 23 October.
  5. 1993Commercial operation begins in January, when the Power Transmission Systems Act transfers ownership of transmission assets held by three power companies.
  6. 1994The company takes over the Southern Regional Load Despatch Centre and transmission assets from Neyveli Lignite Corporation.
  7. 1995Management of the Eastern Regional Despatch Centre and the North Eastern Load Despatch Centre passes to Power Grid.
  8. 1996The Northern and Western load despatch centres complete the set, so all five regional centres are now run by the company.
  9. 1998Power Grid is recognised as a Mini-Ratna Category I public sector undertaking in October.
  10. 2001The Department of Telecommunications grants an Infrastructure Provider II licence so the company can lease spare bandwidth on its own network.
  11. 2002Unified load despatch and communication schemes are commissioned for the northern and southern regions, and the 2,000 MW Talcher to Kolar bipolar HVDC link is commissioned.
  12. 2003A joint venture with Tata Power is set up for part of the transmission system of the Tala hydro electric project, the first public private partnership in Indian transmission, and the 400 kV Raipur to Rourkela line is commissioned.
  13. 2005The unified load despatch and communication scheme for the eastern region is commissioned.
  14. 2006The western region scheme is commissioned, and agreements are signed with REC and state utilities for rural electrification under the Rajiv Gandhi Grameen Vidyutikaran Yojana in nine states.
  15. 2008The 202 kilometre 220 kV double circuit line from Pul-e-Khumri to Kabul in Afghanistan is completed, funded by the Government of India.
  16. 2009The National Load Despatch Centre is established for coordination at the national level.
  17. 2012The northern grid collapses in the early hours of 30 July and fails again on 31 July, when three regional grids go down and 21 states lose supply.
  18. 2019The government confers Maharatna status on Power Grid in October.
  19. 2020PowerGrid InvIT is set up in September as an irrevocable trust sponsored by the company.
  20. 2021The InvIT initial public offering opens on 29 April and is subscribed 4.83 times, the second such offering in the country.
  21. 2021In March the company agrees to buy 74 per cent of Jaypee Powergrid from Jaiprakash Power Ventures for about 351.65 crore rupees, which makes it a wholly owned subsidiary.
  22. 2024Audited results for the year 2023-24 report revenue of about 46,913 crore rupees, a net profit of about 15,573 crore rupees and 8,316 employees in March 2024.

What it does

Power Grid Corporation of India Limited is an Indian central public sector undertaking owned by the Ministry of Power, and it is engaged mainly in the transmission of bulk power across the states. It is headquartered in Gurugram, Haryana, and it transmits about 50 per cent of the total power generated in India on its own network.[1]

The business has four segments. Transmission is the main one and consists of building, owning and operating extra high voltage alternating current and high voltage direct current lines and substations. Consultancy sells the company's engineering and project management experience to state utilities and to other countries. Telecom uses the spare optical fibre along the transmission lines to sell bandwidth. The load despatch business, now carried through a separate company, runs the regional and national control centres that balance generation against demand minute by minute.[1][2]

The network numbers explain why the company is treated as strategic infrastructure rather than as an ordinary listed firm. Power Grid operates about 1,68,140 circuit kilometres of transmission lines and 252 substations with a combined transformation capacity of about 4,22,430 MVA, and it covers about 90 per cent of the country's inter state and inter regional transmission system, with availability above 99 per cent. Its inter regional transfer capacity is about 75,050 MW.[1]

History

The company was incorporated on 23 October 1989 under the Companies Act 1956 as the National Power Transmission Corporation Limited, with an authorised share capital of 5,000 crore rupees that was later raised to 10,000 crore rupees in 2007-08. It was created as a public limited company wholly owned by the Government of India, with the mandate to plan, execute, own, operate and maintain high voltage transmission systems for the country. The Certificate for Commencement of Business came on 8 November 1990, and the name was changed to Power Grid Corporation of India Limited on 23 October 1992.[1][2]

Management began functioning in August 1991, and the company then took over transmission assets from the National Thermal Power Corporation, the National Hydroelectric Power Corporation, the North Eastern Electric Power Corporation, Neyveli Lignite Corporation and others such as NPC, THDC and SJVNL in a phased manner. Commercial operation began in January 1993, and in the same month the Power Transmission Systems Act transferred ownership of the three power companies' transmission systems to Power Grid, with their employees moving across as well.[1]

Between 1994 and 1996 the company took over the regional load despatch centres from the Central Electricity Authority, upgrading them with unified load despatch and communication schemes, and in 2009 it set up the National Load Despatch Centre for coordination at the national level. The mandate was widened at the same time: besides providing transmission for the evacuation of central sector power, Power Grid is responsible for establishing and operating regional and national grids so that power can be transferred within and across regions with reliability, security and economy.[1]

Recognition followed performance. The company was named a Mini-Ratna Category I public sector undertaking in October 1998, a Navratna in May 2008 and a Maharatna in October 2019, each step giving the board more authority to approve investment without referring every proposal to the ministry.[1][2]

Founders and leadership

Power Grid has no private founder. It was created by the Government of India in 1989 under the Ministry of Power, which remains its administrative ministry and its largest shareholder, and the company describes itself as a Schedule A Maharatna public sector enterprise of the Government of India.[2]

The company is led by a chairman and managing director appointed by the government, with Vamsi Rama Mohan Burra holding that office. Its operations are organised through regional headquarters and through national transmission asset management centres, with the NTAMC at Manesar and the RTAMC running the assets using remote monitoring and control.[1][2]

Government ownership shapes the strategy in a way that a private utility would not face. Tariffs for transmission are set by the Central Electricity Regulatory Commission on a regulated return on capital employed, so the company earns a predictable spread on whatever it builds, and in exchange it is expected to build what the national plan needs even where the immediate commercial case is weaker. That is the reason the network reaches the north east, Kashmir and the island territories.[2][3]

The national grid and the transmission network

The core asset is what the company calls the National Grid, a country wide transmission system that lets surplus power in one region be sent to a deficit region. Examples of the stations it owns include the Vizag and Chandrapur back to back HVDC converter stations and the Talcher to Kolar HVDC system, all of which exist to push large blocks of power between regions that run on different frequencies or are too far apart for a plain alternating current line.[1]

The build out has been steady rather than sudden. As of 31 January 2021 the network ran to about 1,68,140 circuit kilometres of line and 252 substations, with transformation capacity of about 4,22,430 MVA and availability of over 99 per cent. The inter regional capacity reached about 75,050 MW, which is what makes a national market in electricity possible at all, because a state that is short can buy from a state that is long instead of starting its own plant.[1]

In 2009 the company reported that the Ranchi to Sipat line had raised the transfer capacity between the eastern and western regions to about 3,000 MW, lifting the inter regional capacity of the National Grid to about 18,700 MW from about 17,000 MW, and it said it planned to take that figure past 37,000 MW by the end of the Eleventh Five Year Plan at an investment of about 55,000 crore rupees.[4]

Since then the mix of the grid has changed. Renewable energy from Rajasthan, Gujarat, Tamil Nadu and the western coast has to be carried to load centres far away, and the company's newest lines are being built for that purpose, including high capacity corridors to move solar and wind power. The dedicated transmission line business for Indian Railways and other bulk consumers is a newer offering that uses the same right of way.[2]

Green energy corridors and evacuating renewables

India's solar and wind capacity is concentrated where the sun and the wind are, in Rajasthan, Gujarat, Tamil Nadu and a few other states, while a large part of the demand sits elsewhere. A renewable plant that cannot be connected is worthless, so the country's renewable target is really a transmission target as well, and Power Grid is the principal builder of the dedicated corridors that carry that power to the load centres. The company's own account of the network notes that the newest lines are being constructed for exactly this purpose, including high capacity corridors that move solar and wind power across regions.[1][2]

The programme has moved through editions. The third edition of the Green Energy Corridor scheme, reported in 2026, is to add about 51,126 circuit kilometres of transmission line and about 50 gigawatt hours of battery energy storage, a scale that shows how the exercise has grown from connecting individual solar parks to planning the grid around the generation mix of the 2030s. Battery storage alongside the lines matters because a corridor can only be used at the capacity of the plant behind it unless there is something to smooth the output, and pairing the two in one programme is a recognition that evacuation and storage are the same problem seen from two ends.[12]

The cost of the delay is measured in curtailment. When generation is built faster than the wires that carry it, the system operator has to instruct renewable plants to back down even though the power is free, and in 2026 the secretary of the Ministry of New and Renewable Energy said publicly that transmission delays rather than excess capacity were behind the curtailment of renewable energy. That statement put the corridor programme at the centre of the country's renewable targets, because every gigawatt commissioned ahead of its evacuation line is a gigawatt that earns nothing while it waits.[17]

The policy setting that makes the corridors viable is the waiver of inter state transmission charges for renewable projects, which was extended more than once to keep new solar and wind capacity economically attractive while the network catches up. The waiver shifts the cost of the wires into the general transmission pool, so it is reviewed and renewed rather than treated as permanent, and each renewal is watched closely by the developers and by the transmission licensees whose revenue depends on it. Behind it sits the national target of 500 gigawatts of non fossil generating capacity by 2030, which cannot be reached without a transmission system built ahead of the plants rather than behind them.[1][12]

For Power Grid the consequence is double edged. Every corridor is capital expenditure that earns either a regulated return or a bid tariff, so the renewable build out is the growth engine of the transmission business and the reason its order book stays full. At the same time the ministry and the regulator press for the completed assets to be monetised through the InvIT route and for the new ones to be won competitively, which caps the return that the company can earn on the capital it spends. Building fast enough for the energy transition and earning a regulated return while doing it is the central tension of its next decade.[6][13][3]

HVDC and the technology of the grid

Power Grid's engineering reputation rests on high voltage direct current links, which are used where an alternating current line cannot do the job. The Talcher to Kolar system, commissioned in 2002 as a 2,000 MW bipolar link, carries coal fired power from Odisha to Karnataka over roughly 1,400 kilometres, and it was one of the largest such systems in the world when it was built. The back to back stations at Vizag and Chandrapur link grids that are not synchronised with each other.[1]

The company also runs the unified load despatch and communication schemes that tie the regional control centres together, starting with the northern and southern regions in 2002 and followed by the eastern region in 2005 and the western region in 2006. These schemes are why a system operator can see the frequency and the flows across the country and instruct a state to back down when the grid is stressed.[1]

The commercial value of the technology is indirect. A better connected grid lowers the cost of power for everyone, because the cheapest generating station can be despatched regardless of where it is, and it reduces the amount of spare capacity each state has to keep for its own peak. The company earns its return on the capital it spends, so technical choices that raise the transfer capacity per rupee of line are the ones that matter.[1]

How a transmission utility earns: tariffs, availability and the regulator

Power Grid does not sell electricity, it sells the right to use a wire, and that single sentence explains most of its financial behaviour. Its revenue is a transmission charge paid by the beneficiaries of the national grid, which are the distribution companies, the generating stations and the large bulk consumers, in return for the capacity the company makes available to them. For the central sector assets the charge is fixed by the Central Electricity Regulatory Commission, which allows a regulated return on the equity invested in each asset, and that is why the business is described inside the industry as an annuity: once a line is commissioned and its cost is approved, its revenue is broadly known for decades.[1][2]

The tariff design rewards availability rather than throughput, which is the opposite of how a highway operator is paid. Under the availability based tariff regime introduced in 2000 the regulator created a structure of incentives and disincentives tied to the frequency of the grid, aimed at making generators and buyers answer for the power they committed to inject or draw. The principle was later applied to transmission itself: a line or a substation that stays available above its target earns a higher return, and one that is out of service earns less, so the company is paid for keeping the lights on rather than for moving more units of electricity.[16]

The regime was a response to specific failures. The regulator was trying to stop rapid frequency deviations away from 50 hertz, which damage industrial equipment, and the repeated grid disturbances in which generators tripped and the system split. By putting a price on deviation, ABT made an over drawing state and an under injecting generator pay for the disturbance they caused, and the mechanism was eventually extended from the central sector to the state systems. It is also the reason the collapse of July 2012 had a commercial dimension and not only an operational one: the utilities that kept drawing beyond their schedule were not merely ignoring an instruction, they were avoiding a charge.[16][11]

New lines are now built under a different rule. When a project is awarded through tariff based competitive bidding the tariff is discovered in an auction for a period of about thirty five years instead of being fixed by the regulator, and the winner is whoever offers to build and run the line for the lowest charge. Power Grid bids through its own subsidiaries against private developers, and about three quarters of the assets that went into PowerGrid InvIT came from exactly this route, which is the clearest sign of how much of the new build is now won rather than assigned. The two regimes run side by side on the same network, with regulated returns on the older assets and discovered tariffs on the newer ones.[6][14]

In practice the money reaches the company through a point of connection mechanism, under which users of the inter state system pay transmission charges that are collected centrally and then shared among the transmission licensees in proportion to the assets each one uses. That is why the regulator's sharing regulations matter to the company's revenue as much as its own capital expenditure plans do. Congestion on the network has been small in relation to its size, with about 0.3 per cent of the electricity consumed in the financial year 2013-14 bought but not transmitted, and the corridor programme in the 2020s is designed to keep that number small as renewable capacity is added at the far ends of the country.[16][2]

Powertel and the telecom business

Powertel is the telecom arm, and it exists because a transmission tower is also a place to string optical ground wire. Its network runs about 1,00,000 kilometres with points of presence in more than 3,000 locations across the country, and it sells bandwidth along those routes.[1][5]

The licences give it more room than a pure infrastructure provider. The company holds a national long distance licence and an internet service provider Category A authorisation, which lets it sell enterprise services such as MPLS VPN and internet access with defined quality of service and class of service commitments, and it acts as a neutral carrier in point to point bandwidth leasing.[2]

The business is a genuine second use of an asset that has already been paid for by the electricity customer, which is why its margins look different from those of a telecom operator. It is also small relative to the transmission business, and its main competition is GAIL's GAILTEL, which sells the same kind of spare capacity along gas pipeline rights of way.[2]

Consultancy and international projects

Transmission consultancy turned out to be an exportable skill. The company has provided consultancy to domestic and international clients in power transmission, sub transmission, distribution management, load despatch and communication, and it describes in house expertise in the transmission sector as one of its strengths. Its first international consultancy contract came from Bhutan Telecommunications in 2003.[1][2]

The best known overseas job was in Afghanistan. In January 2009 the company said it had completed a 202 kilometre 220 kV double circuit line from Pul-e-Khumri to Kabul, funded by the Government of India under its assistance programme to the country, which connected Kabul to imported power from the north.[4]

Its consultancy portfolio now includes system studies, design, engineering, load despatch, transmission procurement management, operations and maintenance, project management, smart grid implementation, energy efficiency and energy audits, and capacity building assignments. That is a services business built on the fact that Power Grid solved problems at home that other countries are still working through.[2]

PowerGrid InvIT and asset monetisation

PowerGrid InvIT was formed in September 2020 by the company as sponsor, as an irrevocable trust whose purpose is to hold operating transmission assets and distribute the income to unitholders. It was the company's answer to a simple problem: the network needs far more capital than one balance sheet can raise, and completed lines with fixed long term tariffs are exactly the kind of asset that can be sold to institutional investors.[6]

The initial public offering opened on 29 April 2021 and closed on 3 May, and was subscribed 4.83 times, making it the second InvIT offering in the country. The offer combined a fresh issue of about 4,993.48 crore rupees with an offer for sale of about 2,741.51 crore rupees, at a price band of 99 to 100 rupees a unit, against an offer size reduced by an anchor book that raised about 3,480 crore rupees on 28 April from 34,80,74,100 units.[6]

The initial portfolio was five tariff based competitive bidding projects holding eleven transmission lines of about 3,698.59 circuit kilometres and three substations with about 6,630 MVA of transformation capacity across five states, with the trust holding 74 per cent of each project and the balance to be acquired from Power Grid after a lock in period ending in 2024. The assets carry tariffs fixed for 35 years, which is why the issue was sold on the strength of annuity like cash flows and low counterparty risk.[6]

For the parent, the trust is both a source of cash and a mild transfer of control. Money raised by selling completed assets can be spent on new lines without adding debt, and the government gets part of the proceeds as its share, but each transfer of an asset reduces the regulated capital on which Power Grid itself earns its return. That trade off is the live argument inside the company and inside the ministry.[6][3]

Revenue and financials

Power Grid reported revenue of about 46,913 crore rupees for the year 2023-24, with operating income of about 19,085 crore rupees and a net profit of about 15,573 crore rupees. Total assets were about 2,50,890 crore rupees and equity about 87,145 crore rupees. The workforce stood at 8,316 employees in March 2024, which is a small number for an asset base of that size.[1]

The shape of the profit is unusual for an infrastructure company, because the return is regulated. The Central Electricity Regulatory Commission allows a fixed return on the equity invested in each completed asset, so revenue grows when the company commissions new lines and stays broadly stable when demand falls. Availability of over 99 per cent protects that income, because a transmission line that is out of service does not earn the incentive that comes with high availability.[1]

Costs are mostly depreciation, interest on the debt taken to build the network, and employee cost, and none of them move much with volumes. That is why the company can carry a very high asset base relative to revenue: the revenue is the tariff, not the value of the electricity carried. The result is a utility whose earnings are predictable enough that it pays a regular dividend and is treated as a bond substitute by many domestic institutional investors.[1][3]

Shareholding and ownership

The Government of India held about 51.34 per cent of Power Grid as on 31 December 2020, and the company's own overview page describes that holding as 51.34 per cent with the balance 48.66 per cent held by institutional investors and the public. The shares trade on the Bombay Stock Exchange under code 532898 and on the National Stock Exchange under the symbol POWERGRID, and the scrip is part of the Sensex and Nifty indices.[1][2][7][8]

The stake used to be larger. An exchange filing and press reports in 2020 put the government holding at 54.96 per cent and described a plan to bring it down to 51 per cent through an exchange traded fund route, one round of a wider disinvestment programme. NTPC and Power Finance Corporation were in the same position, and all three told the ministry of power that a fall below 51 per cent could raise their cost of borrowing, because international lenders and rating agencies have priced in the assumption of state control.[3]

That concern is easy to understand in Power Grid's case. The company borrows heavily to fund a network that earns a regulated return, so an increase of even a fraction of a percentage point in the cost of debt is a real cost over a twenty year asset life. The government has kept management control and the stake has stayed just above the majority mark.[3]

Employees and offices

Power Grid had 8,316 employees in March 2024. The workforce is heavily technical, made up of electrical engineers, system operators, protection and control specialists and project managers, because a transmission utility is run from control rooms and substations rather than from offices.[1]

The headquarters is in Gurugram, and the country is divided into regional and zonal offices that follow the geography of the grid rather than of the states. Day to day operation of the assets is carried out from the NTAMC at Manesar and the regional transmission asset management centres, which monitor substations remotely and despatch maintenance teams. The load despatch centres, now run through a separate company, sit alongside this structure and hold the authority to instruct generators and states.[1][2]

Because so much of the work is automated, the company's fixed cost per circuit kilometre is low, and its main people risk is the loss of experience in high voltage engineering. The company runs its own training and knowledge programmes and uses the National Power Training Institute for part of its skill building.[2]

Subsidiaries and joint ventures

Two divisions or subsidiaries carry the non transmission businesses. Powertel India Limited runs the telecom arm, and the Central Transmission Utility of India Limited handles the planning and coordination role that the company used to perform inside its own transmission planning department.[1][2]

In transmission itself the company has used joint ventures and special purpose vehicles, which is how a public sector utility builds a project with private partners. The 2003 arrangement with Tata Power for part of the transmission system of the Tala hydro electric project was the first public private initiative in Indian transmission, and the line it built, the 400 kV Raipur to Rourkela circuit, was commissioned the same year.[1]

Jaypee Powergrid Limited was another such vehicle. Power Grid signed a share purchase agreement with Jaiprakash Power Ventures in March 2021 to acquire the 74 per cent it did not already hold for about 351.65 crore rupees, after which Jaypee Powergrid became a wholly owned subsidiary of the company. The InvIT holds five more such projects at 74 per cent each, with Power Grid holding the remaining 26 per cent until the lock in period ends.[9][6]

Acquisitions and project execution

Power Grid's growth has come from building rather than buying, and its acquisitions are mostly about tidying up the ownership of assets it already operates. The Jaypee Powergrid purchase in March 2021 is the clearest example: the company already had a stake in the joint venture, and buying out the partner's 74 per cent for about 351.65 crore rupees settled the ownership of the line. The market reaction that day was a two per cent fall in the share price, which is what a large, low drama infrastructure acquisition usually produces.[9]

The other side of the acquisition question is outsourcing. Because the company's own workforce is small, most of the physical building is done by contractors, and orders to equipment makers are a regular feature of its year. One such order, worth about 108 crore rupees to Transformers and Rectifiers for the supply of transformers, is typical of the hundreds of procurement contracts that turn the capital expenditure plan into towers, conductors, transformers and switchgear.[10]

The InvIT structure is the closest thing to a portfolio transaction the company runs. Selling completed lines into a trust and using the proceeds to fund the next set of lines is a way of recycling capital, and it means the company's future asset base is decided as much by what it can sell as by what it can build.[6]

Competition

In its main business Power Grid faces almost no direct competition, because it owns the bulk of India's inter state transmission system and the regulator grants a regulated return on the assets it builds. The Electricity Act of 2003 opened transmission to private participation, and new lines are now awarded through tariff based competitive bidding, which means the company competes for the right to build a specific line through its own subsidiary, Power Grid Corporation of India, against bidders such as Tata Power, Adani Transmission, Sterlite Grid and the Power Finance Corporation sponsored entities.[1]

On those bids the company's advantages are engineering depth, an existing right of way corridor and a lower cost of funds, while its disadvantage is that a public sector board has to clear a bid through its own investment rules. Three quarters of the assets in PowerGrid InvIT came from exactly this competitive route, which shows how much of the new build is now won rather than assigned.[6]

In telecom the competitor set is different, with private operators and GAIL's GAILTEL selling the same kind of wholesale capacity, and in consultancy the company bids against private engineering firms and against other public sector consultants. In both cases the brand matters less than the route and the price, and both are small enough that they do not change the investment case either way.[1][2]

The 2012 blackouts and grid stability

The worst day in the company's operating history came in July 2012. At about 2.35 in the morning on 30 July the Northern Region Grid, which supplies nine states including Delhi, was hit by a disturbance and failed, and Power Grid and POSOCO began restoring supply immediately. Essential services were back by 8 in the morning, about 60 per cent of the normal northern load was restored by 11, and most cities and towns had power by 12.30 in the afternoon, with the region back to meeting a demand of about 30 GW by 7 in the evening.[1]

The next day it happened again, and much worse. In the early afternoon of 31 July the northern, eastern and north eastern grids failed together, leaving 21 states and half the country without power for several hours. About 200 miners were trapped in the Eastern Coalfield at Burdwan in West Bengal and another 65 at the Bharat Coking Coal facility in Jharkhand, and trains stopped across large parts of the network. By late evening about 25,000 MW of the 50,000 MW affected had been restored, and supply was extended from the western and southern grids.[11]

The reported cause was grid indiscipline rather than a failure of the transmission lines. Utilities in Uttar Pradesh, Haryana, Punjab and Rajasthan were said to have kept drawing more power than their schedules allowed, despite warnings from the Northern Regional Load Despatch Centre, and most had not installed under frequency relays that would have shed load automatically before the system collapsed. Punjab rejected the charge. The then power minister, Veerappa Moily, said the grids would be independently audited within three months to make them fail safe.[11]

The episode is still the reference point for why load despatch discipline and frequency control matter. The company's own role was to restore the system, and it did that within hours rather than days, but the reporting made clear that a transmission utility can only be as reliable as the states that treat the grid as a shared resource.[1][11]

Grid operations and the separation of POSOCO

Running the wires and running the system turn out to be different jobs, and the law now treats them as such. The load despatch function decides whose power is generated at any moment: the system operator schedules the stations, watches the frequency, instructs a plant to increase or back down, and settles the deviations from the schedule. Power Grid took over the regional load despatch centres from the Central Electricity Authority between 1994 and 1996 and ran them for years, until the Electricity Act of 2003 required the commercial interest in transmission to be separated from the neutral management of the system.[15][1]

The separation happened in stages. Following the Pradhan Committee's report on ring fencing the load despatch centres, the government notified in September 2010 that Power System Operation Corporation, POSOCO, would operate the National Load Despatch Centre and the five regional centres, and it began doing so on 1 October 2010 as a wholly owned subsidiary of Power Grid. It was made a separate company with effect from 2 January 2017, and on 9 November 2022 it was renamed Grid Controller of India Limited, known as GRID-INDIA. What began as a unit inside the transmission utility ended as an independent organisation responsible for the round the clock operation of the Indian power system.[15]

The argument for the split is about conflict of interest rather than about efficiency. A company that owns most of the transmission system and also decides which generating station is despatched has an interest in the answer, because the system operator's instructions determine whose electricity is bought and therefore whose revenue is earned. The committee that recommended the change wanted the load despatch centres to be financially self reliant and autonomous, with their own board and their own revenue streams, so that a despatch decision could not be traced back to a transmission commercial interest. The collapse of July 2012, in which states drew far beyond their schedules despite warnings from the Northern Regional Load Despatch Centre, is still the reference point for why that neutrality matters.[15][11]

GRID-INDIA now does the work that used to sit inside Power Grid. It schedules and despatches generation, monitors the frequency of the national grid, administers the deviation settlement mechanism that ABT introduced, and runs the renewable energy management centres that forecast solar and wind output so that a variable generator can be integrated without destabilising the system. Power Grid kept the wires, the substations and the converter stations; GRID-INDIA took the control rooms. The two organisations share a system and a set of data, and the boundary between them is one of the more carefully drawn lines in Indian infrastructure regulation.[15][16]

The effect on Power Grid itself is modest in money and significant in accountability. The company gave up a small internal revenue line and, with it, an exposure that could not be managed: when the grid fails, the organisation that gives the instructions is the one that has to explain them. Power Grid's own responsibility is now confined to the availability and reliability of its assets, which is precisely the number the regulator measures, rewards and penalises. In an industry where a single collapse can darken half the country, being paid for availability rather than for authority is a narrower job and a more defensible one.[15][1]

Controversies and criticism

The criticism the company encounters most often is about money rather than engineering. Selling completed transmission assets into an infrastructure investment trust transfers income that Power Grid itself used to earn, and the argument against the model is that the country's grid operator is trading a permanent regulated return for a one time cash payment. The argument for it is that the alternative is to borrow more, and that the network cannot be built fast enough on one balance sheet.[6]

The second recurring argument is about transparency in bidding for new lines. Because the company competes for projects it also plans and operates, its position in tariff based competitive bidding has been questioned by private developers, who have said that the operator of the grid should not also be a bidder for the lines that the grid needs. The company's answer is that the planning role has been separated into the Central Transmission Utility of India Limited.[1][2]

A third theme is land and right of way. Every extra high voltage line needs a corridor across farmland, forest and sometimes inhabited land, and compensation and clearance disputes have been a repeated source of delay for transmission projects of this kind across the country. The company works within the framework set by the states and the Central Electricity Regulatory Commission, and its availability figures are strong, but the slowest part of any new corridor is usually the negotiation on the ground rather than the engineering.[1]

Environmentally, Power Grid is on the easier side of the energy debate, since it moves electricity rather than burning fuel, and a better connected grid is what allows renewable energy to displace coal. The criticism that does land is about the footprint of the lines themselves, including tree felling along corridors and the visual and land use effect of high towers, which is the price the system pays for carrying power between regions.[1][2]

Reading the numbers

Three figures carry the story. The first is about 1,68,140 circuit kilometres of line and 252 substations, because the physical network is the business and the regulated return is calculated on the capital sunk into it. The second is about 50 per cent of India's generated power travelling over those lines, which is what makes the company systemically important. The third is the shareholding of about 51.34 per cent with the government, because it sets the credit rating, the cost of debt and the way the company is judged by the state as an instrument of policy as well as a listed company.[1][2]

Revenue of about 46,913 crore rupees against a net profit of about 15,573 crore rupees in the year 2023-24 gives a margin above thirty per cent, which looks extraordinary next to a manufacturer or a refiner and is entirely normal for a regulated transmission utility. The reason is that the tariff is set to recover cost plus a return rather than to win a market, and the big costs, depreciation and interest, are themselves consequences of the asset base that earns the return.[1]

The thing to watch over the next few years is the split between the lines the company owns and the lines the InvIT owns, and the pace at which new renewable corridors are commissioned. A growing network built through competitive bidding and partly funded by asset sales is a different company from the one that took over NTPC's transmission assets in 1993, and the investment case now depends on winning and delivering projects rather than on being the only available builder.[1][6]

Related entries

OrganizationNTPC LimitedThe country's largest power producer, whose stations fed the transmission assets Power Grid took over in 1993 and still depend on the national grid.OrganizationCoal IndiaThe state coal producer that supplies the fuel for most of the thermal generation the transmission network carries.OrganizationLarsen and ToubroThe engineering group that builds transmission lines, substations and power plants for utilities such as Power Grid.OrganizationGAIL (India) LimitedThe state gas transmission company, whose pipeline corridors carry the same kind of right of way and telecom capacity as Power Grid's lines.
OrganizationCompanyElectricityTransmissionNational GridGovernment of IndiaGurugram

Sources

  1. Wikipedia, Power Grid Corporation of India
  2. Power Grid Corporation of India, Company overview
  3. The Economic Times, Power companies feel divestment may increase cost of borrowings
  4. Business Standard, PowerGrid completes transmission line in Afghanistan
  5. Power Grid Corporation of India, Telecom
  6. Moneycontrol, PowerGrid InvIT IPO subscribed 4.83 times, QIB portion booked 4.63 times on final day
  7. Bombay Stock Exchange, Power Grid Corporation scrip page
  8. National Stock Exchange, Power Grid Corporation of India Limited quote
  9. Business Today, Power Grid to buy 74% stake in Jaypee Powergrid, stock drops 2%
  10. ETEnergyworld, Transformers and Rectifiers bags Rs 108 crore order from PGCIL
  11. The Hindu, Day two: 21 States plunge into darkness as 3 grids collapse
  12. Times of India, Third edition of Green Energy Corridor to add 51,126 ckm transmission lines and 50 GWh BESS
  13. Times of India, In 1st for PSU, PowerGrid files for Rs 8,000 crore InvIT listing
  14. Times of India, Pvt cos target PowerGrid in fight for transmission pie
  15. Wikipedia, Grid Controller of India Limited
  16. Wikipedia, Availability-based tariff
  17. Times of India, Transmission delays behind RE curtailment, not excess capacity: MNRE secy

Related entries

Company · organizationAdani GroupAdani Group is an Indian conglomerate in ports, power, coal, gas, airports, cement and green energy, founded by Gautam Adani in 1988 from Ahmedabad.Company · organizationAdani Ports and Special Economic ZoneAdani Ports and Special Economic Zone is India's largest private port operator, running Mundra, Dhamra and a dozen ports and terminals in India and overseas.Company · organizationAditya Birla GroupAditya Birla Group is an Indian conglomerate based in Mumbai, with businesses in cement, aluminium, fibre, chemicals, financial services and fashion.